Premier Pipe > Articles

Do you have questions?

Give us a call or send us an email  we’re always here to help answers your questions.

Contact Us

Articles

PREMIER PIPE USA™ PROUDLY PRESENTS S.B. LINER – Trenchless Technology


Spout Run CIPP project proves with proper planning anything is achievable

Read More


PREMIER PIPE USA™ PROUDLY PRESENTS S.B. LINER – Trenchless Technology

Premier Pipe USA™ S.B Liner is a groundbreaking proprietary styrene barrier coated product, which is named after our Premier Pipe founder, Mr. Simon Baylis.

Read More


2020 Project of the Year Rehabilitation: Guam Northern Interceptor Sewer Rehabilitation

The Island of Guam provided a tropical and scenic backdrop to an impressive and challenging ultraviolet cured-in-place pipe (UV CIPP) project. In all, 44,000 lf of sewer were rehabilitated — ahead of schedule — as crews managed logistical and planning challenges, as well as working in conditions that included the early stages of a global pandemic.

Read More



2018 Project of the Year Rehabilitation Honorable Mentions

Emergency 30-in. Force Main Replacement

north area interceptor phase 9

North Area Interceptor Phase 9

Michels was the general contractor on a large-scale project to rehabilitate nearly a mile of deteriorating high-capacity regional sanitary sewer facilities that serve Fridley, Spring Lake Park, Coon Rapids and Blaine — the northwestern suburbs of the St. Paul-Minneapolis, Minnesota, metropolitan area.

The project included constructing a temporary conveyance system to maintain wastewater services throughout the duration of the project. The system consisted of three 30-in. sections of HDPE, each totaling 5,100 ft, to convey an average daily flow of 25,000 gpm of effluent and a peak flow of 52,000 gpm. Seven pumps were also installed on the system. Cured-in-place pipe (CIPP) liners were installed to rehabilitate 3,866 lf of massive 96-in. (8-ft) diameter pipe and 90 ft of 72-in. diameter pipe. The 96-in. CIPP segments were completed in four installations that varied in thickness from 25.5 mm to 34.5 mm and in length from 700 ft to 1,180 ft. Both 72-in. installations were 19.5 mm thick and 45 ft in length. The 96-in. segments were the largest diameter CIPP project Michels has completed, and included a substantial amount of work during Minnesota’s harsh winters.

The project also included rehabilitation of a meter station and manholes. There were eight 72-in. to 120-in. fiber reinforced polymer and concrete manholes installed on the project to replace existing manholes. Due to their large diameter and weight of resin, the CIPP liners were wet out over the hole (OTH) rather than being impregnated off site and transported to the job site. This required trucks to haul 730,000 lbs of resin to the site on days of installation.

If You Need Any Industrial Solution ... We Are Available For You